ಯೋಜನೆಯ ಹಂತ
ಭೌತಿಕ ಪ್ರಗತಿ

Out of 72.29 acre of acquisition of land, 72.00 acres have been awarded. And 69.39 acres compensation has been paid. Balance area of 2.30 acres is yet to be paid to the general award cases. So far an amount of Rs 293 crores as on 31.12.2016 has been paid in the form of compensation to the land losers.

The details of Land to be acquired are as under:

VILLAGE
/ TOWN

Land  to be Awarded

Remarks

Hubli (M.T.Sagar)

0.02

2 gunta general Award approved, the documents are awaited.

Bairidevarakoppa

0.21

Dargah Area- 17 (3) notice issued.

Dharwad City

0.06

6 gunta general Award submitted to DC office for approval

TOTAL

0.29

 

Total Expenditure till date including R&R is Rs. 293 Crores (R&R Rs.1.72 crores)

  • 69.39 acres area has been handed over to EE KRDCL, Hubli.
(ii) RAP Status

Sl. No

Category of PAP

PAPs Shifted from the Corridor

PAPs Yet to be shifted from the corridor

Total Numbers

1

Squatters & Kiosks

85

2 Nos.

87

2

Tenants

310

38 Nos.

348

3

Encroachers

147

1 Nos

148

4

Community Assets

10

7 Nos.

17

 

A) Status of the Works, consultancy services and Goods:

The status of works, consultancy services and goods are as stated below:

The status of the Works undertaken with World Bank Aid.

(i) Status of Infrastructure works:

Package

Scope of work

Present Status

pw 1

Construction of BRTS Bus Stations and pedestrian Infrastructure between Hosur cross to railway station in Hubli City

The Project covers construction of 4 Nos of Bus stations in City limits. The works at Hosur bus station is under progress and rest 3 bus stations require preparatory works like construction of the road and compound wall at Ranichannamma circle, HDMC & BSNL. Work is under progress. The modification to Ranichennamma circle is taken up by National Highway & the Bus station location needs to be redesigned. `

pw 2

Construction Bus terminal at Mitra Samaja in Dharwad

Foundation work up to ground level at Hosur, Perana college and Unkal Lake have been completed, like wise lift Room walls also completed up to ground level and grade beams have been casted at some locations as like Stair walls. Further lift Room walls above the ground level at various locations are in progress.

pw 3 A

Construction of foot over bridges from Ranichennamma circle to Navanagar along Hubli-Dharwad road at Ranichennamma circle, Hosur, Prerana college and Unkal

Foundation work up to ground level at Hosur, Perana college and Unkal Lake have been completed, like wise lift Room walls also completed up to ground level and grade beams have been casted at some locations as like Stair walls. Further lift Room walls above the ground level at various locations are in progress.

pw A B

Construction of Foot Over Bridges from Navanagar to Court Circle Dharwad along the Hubli Dharwad Road at Navanagar, Rayapur, SDM Medical College and Court Circle Dharwad.

At Navanagar and Rayapur the foundation work up to ground level have been completed, like wise lift Room walls also completed up to ground level and grade beams have been casted at Some locations as like Stair walls. Further lift Room walls above the ground level at various locations are in progress. At Court circle electrical utilities have been shifted. Work to be taken up by the contractor.

pw 4

Development of Pedestrian footpath and NMT Infrastructures under Hubli-Dharwad BRTS Project

Navanagar: Eletrical LT UG cabling procurement/laying work under progress at Navanagar.
Dharwad: Drain work is completed from Old DSP circle to Shivaji Circle except for few gaps. As KSHIP is taking up the Road and Drain works. The decision for foreclosing the work of NMT at Dharwad is thought and letter sent to DULT for approval.

pw 5

Construction of BRTS Bus shelters from Naveen Hotel Hubli to Rayapura, Dharwad

Roofing work completed in 11 Bus stations and rolling shelter in 7 bus stations completed. In one Bus station truss errection work is Completed . In Unkal bus station truss work done in only one side and balance on the other side is yet to be completed. In Rayapura Bus station False ceiling work completed. Wooden planks for four bus stations is procured. Out of which KIMS and Navanagar bus station in RTO & APMC teak wood false ceiling work is in under progress.

pw 6

Construction of BRTS Bus shelters from Rayapura, Dharwad to Bagalkot Petrol bunk, Dharwad

Among 13, in 8 bus shelters roofing sheet work has completed. In 3 bus stations, false ceiling work has completed. And in two Bus stations false ceiling work is under progress. In 5 Bus stations RCC work has completed. For errection of trusses in city limits is held up for want of clearance of the local police authority.

pw 8

Construction of BRT Depots in Hubli & Dharwad and Divisional Workshop in Hubli

The financial progress achieved 41% and physical progress 45%. Balance work is under progress. Notice issued to contractor to improve the progress.

pw 9

Construction of Bus Terminal at Old City Bus Station (OCBS) in Dharwad

The contract agreement has concluded with new contractor. Notice to proceed with work is issued. Work under progress.

pw 10

Construction of Depot & Regional Terminal at Hosur road, Hubli

Overall 75% of the works are completed. Finishing work as under progress at block-B & Block-C. Pavement (DLC & PQC) is under progress. Other works are under progress & expected to be completed by May 2017

(iii) Status of Infrastructure works:

(i) Status of Plant/ Equipments and ITS works:

Package

Scope of work

Present Status

PW7

7A- Purchase of Plant and Equipment to BRTS depots and Workshop

Tender process is completed and Letter of Award has been issued to the Suppliers for the supply of 32 equipment.

7B- Purchase of Equipment to Tyre Retreading Plant

Tender has been floated for the purchase of these equipment. 3 bids have been received and all the bids were non responsive. Hence rebidding process is under progress.

PW 11

11A. Procurement of Intelligent Transport System (ITS) for Hubli-Dharwad BRTS Corridor.

Agreement is entered with M/s NEC India Pvt. Ltd. its consortium on 29/11/2016 for the Design, Supply, Install, Commission and Maintain ITS System for BRTS corridor, duly following the World Bank procurement guidelines.

11B. Procurement of Platform Screen Doors (PSD) for BRTS bus stations

Letter of Award has been issued to M/s Technocrats Security Systems Pvt. Ltd. on 19/12/2016 duly following the World Bank procurement guidelines.

11C. Turnkey implementation of Adaptive Traffic Control System (ATCS) in Hubli-Dharwad BRTS Corridor

Memorandum of Agreement (MoA) is entered with M/s CDAC, Tiruvananthapuram on 30th Aug 2016 for Traffic Management with ITS which includes preparation of DPR, installation and operation of ATCS at 43 junctions and 10 midblock locations and setting up of Traffic management Centre to monitor and manage signalling system at Hubli-Dharwad.

Procurement of Rolling stock

1

Procurement of 100 nos of 12 meter, premium, AC, BRTS buses.

The purchase order is place on M/s Volvo India Pvt. Ltd. for the supply of these buses. The prototype bus is ready and the deliveries are scheduled from March 2017.

2

Procurement of 30 nos 18 meter, AC Articulated BRTS buses.

The purchase order is placed on M/s TATA Motors Ltd. for the supply of these buses. The construction of prototype is under progress.

(iii) Related Works undertaken with GOK funds

Sl NO

Name of the work

Present status of the work

1

Construction of Compound Walls for Govt Lands along the BRT Corridor

Completed

2

Demolition/dismantling of the structure from Hosur to Tollnaka.

Work is under Progress. 26 nos of the properties are to be demolished. 

3

Demolition/dismantling  of the structure from Tollnaka to Jublie Circle, Dharwad City

Work is under Progress. 53 nos of the properties are to be demolished. 

4

Construction of Compound Wall to the Government Offices/School/Garden/Organization along BRTS Corridor in between Hubli and Dharwad (2nd Tranche)

Work is under Progress at KMF, Court Circle.  

5

Construction of Roads opposite to Old Bus stand and HDMC in Hubli

Work is under progress

6

Construction of Compound wall and associated civil works at HDMC & BSNL Sanchar Sadan on Lamington Road, Hubballi

Work is under progress.

7

Transit Oriented Development at Navangar in Hubballi

Tender floated on 18-11-2016. Last date for bid submission is fixed 18-01-2017

(iv) Works Implemented by KRDCL

A ) Construction of Mixed Traffic Lane Road Work

Sr. No.

Activity

Total Length (in KM) Completed.

Total

LHS

RHS

1

Excavation up to Sub grade TOP

3.378

5.375

13.238

2

Sub grade top

2.800

1.685

3

GSB Top

3.978

3.978

7.408

4

WMM Top

3.820

1.890

5.710

5

DBM Top

3.576

1.870

5.446

v) Construction of Balance BRTS Corridor: Work is in progress: Initial CD surveys and inventory is under progress.
vi) Construction of 3 Nos Grade Separators

Sl No

Grade Separator location

Present work

At

Km/Chinage

Total Length

From

To

1

Navanagar

(Ch 6.656)

(Ch 7.51)

854 m

All the works are expected to be completed by 15th Dec 2016 and BRTS company and KRDCL jointly working on to make an event to allow traffic on Navanagar grade separator on trial basis from 1st Jan 2017.

2

Unakal Lake

(Ch: 3.120)

(Ch: 3.575)

475 m

Pier caps work under progress and girder casting works under progress.

3

Unakal Cross

(Ch: 2.325)

(Ch: 2.950)

625 m

Diversion road work Completed. Safety Arrangements at site are under progress.

(vii) ) Construction of Rail over Bridge ( ROB)

Sl No

Components

Progress

1

Test Pile

Testing of Pile Completed

2

ROB portion Pier Works

-

3

Viaduct Portion Pier Works

Out of 16 Piles, 6 Pile concreting Completed.

4

Box Under Pass

Box Raft work completed. Substructure work under progress.

5

Cattle Pass

Raft work Completed. Substructure work under progress.

6

Extension of CD

Raft work Completed. Substructure work under progress.

7

Reconstruction of CD

Raft work Completed. Substructure work under progress.

8

Tadasinakoppa Village Road

C&G works under progress.

9

Drain Work

Preliminary works are under progress

10

RE Panel cast and erection

1348 Nos RE panels cast and excavation for erecting the Panel is under Progress.





  1. Status of Consultancy services

1

Consultancy for Monitoring & Evaluation for BRTS (Social safeguards)

As per the revised agreement, the consultant has submitted 10th quarterly report and draft interim report submitted on 19.09.2016. soft copy the same has been scrutinised by HDBRTS and sent to DULT for review.

2

Consultancy for Communication and Outreach

Contract period is ended in February 2016. The consultant has carried out all the required outreach activities except 14 activities out of which 13 activities are related to pre launch and post launch of operations.

3

Project Management Consultants for BRTS

Consultancy Services was awarded to LASA, Delhi for an amount of 5.14 Cr.  Consultancy services as per TOR are undertaken by LASA.
Extension of the proposal with actual man months required has been submitted to PMU ( SUTP) for approval.

4

Project Management Consultancy for ITS

The Contract period was expired in July 2016. The proposal was submitted to World bank/SUTP for the extension of contract and requested for NOC. SUTP has given approval for the same. The agreement needs to be entered for the extended period.

5

Consultancy Services for Preparation of City Plan for Hubli - Dharwad

The Company has entered into an Agreement with M/s IBI Group On 8th December 2015 for the preparation of city plan of Hubli-Dharwad. The Consultant has submitted the inception report. Further reports are under progress.

6

Consultancy Services for Environment Audit

The agreement between HDBRTS Co Ltd and ERNST AND YOUNG Private Ltd has been concluded on 24-12-2014 The consultants submitted 2nd audit report which is under scrutiny for compliances.

7

Consultancy services for development of landscape plan for Hubli-Dharwad BRTS Project

The consultants submitted concept plans in the June, 2016 as a 2nd stage milestone and working on further stages.

(vii) ) Plantation Status under Green BRTS.

Sl No

Details

Trees planted

Location

Trees surviving

Executing Agencies

1

Phase -1 (2013-2014)

8000

At various schools and Institutes in Hubli & Dwd

2252

HDBRTS & Beneficiary institutes

 

2

Phase -2 (2014-2015)

4000

Hubli-STP Gabbur, Nrupatunga beta. Dwd- Tapovana, Shri Ram nagar, Gandi nagar school.

3040

KFD

 

3

Phase -3 (2015-2016)

1800

Hubli-STP Gabbur, Nrupatunga beta, Revenue colony (Nr channamma nagar). Dwd – Govt Jr collage & new bus stand.

1435

KFD

 

4

Phase -4 (2016-2017)

8000

Navalur Betta Dharwad.

Survival rate will be known in Monsoon 2017

KFD

Out of 11000,  8000 are planted and remaining 4000 will  be planted in next rainy season during  2017