PROJECT STATUS
(i) LAQ Status

Out of 72.29 acre of acquisition of land, 72.00 acres have been awarded. And 70.00 acres compensation has been paid. Balance area of 2.00 acres compensation payment is in progress. So far an amount of Rs. 303 crores as on 15.06.2017 has been paid in the form of compensation to the land losers

The details of Land to be acquired are as under:

VILLAGE/ TOWN

Balance Area

Remarks

Hubli (M.T.Sagar)

0.02

2 gunta  general Award approved, the documents are awaited.

Bairidevarakoppa

0.21

Dargah Area- 17 (3) notice issued.

Dharwad City

0.06

6 gunta  general Award submitted to DC office for approval

 Total

0.29

 

Total Expenditure till date including R&R  is Rs. 302.59 Crores (R&R Rs.2.34 crores)

  • 70.00 acres area has been handed over to EE KRDCL, Hubli.
(ii) RAP Status

Sl No

Category of PAP

PAPs Shifted from the Corridor

PAPs Yet to be shifted from the corridor

Total Numbers

1

Squatters & Kiosks

87

-

87

2

Tenants

338

10

348

3

Encroachers

148

-

148

4

Community Assets

10

7 Nos

17

 

Status of the Works, consultancy services and Goods:

The status of works, consultancy services and goods are as stated below:

The status of the Works undertaken with World Bank Aid.

(i)Status of Infrastructure works:

Package No

Scope  of the work

Present Status

PW1

Construction of BRTS Bus Station and pedestrian infrastructure between Hosur to Railway station in Hubli

BSNL & HDMC – Roof Beams are erected and further works under progress
 Ranichannamma – Existing FOB will be removed and constriction work will be start shortly.

PW2

Construction terminal building at Mitra Samaja in Dharwad.

Basement slab is completed. Ground Floor works under progress.
Plumbing and utilities, floor PCC and grade slab work in progress
3 lifts of wall concreting completed for water tank and pump room & LHS, RHS wall, water tank. Articulated plat form constriction under progress.

PW3 A

Construction of foot over Bridges from Rani Chennamma circle to Navanagar,  at  Ranichennamma circle, Hosur, Prerana College and Unkal

Hosur FOB: Median first ramp concreting is completed. Individual column for second ramp concreted.  Lift portion completed. Slab connecting Hosur interchange and lift and C4 concreted, C5 preparation is in progress.
Prerana College: staircase works under progress.
Unkal Lake FOB: LHS first ramp and lift shaft for third lift completed. Work under progress for second ramp and final lift.
Median : Grade slab works under progress.

PW3 B

Construction of foot over bridges from Navanagar to Court Circle Dharwad. Along the Hubli Dharwad Road at Navanagar, Rayapur  and Court circle Dharwad.

Navanagar FOB: LHS all the ramps and lift upto 5.5 mtr level completed. C5 column final level preparations in progress. RHS : grade slab wall preparation in progress.
Rayapur FOB: Girder fabrication is in progress for half portion and is expected to commission in next two days.
LHS : ramp preparation for second no is in progress.
PCC for approach walkway completed and reinforcement is in progress.
Median: All the ramps completed including lift upto 5.5 mtr level.
RHS : First ramp is completed preparation for second ramp is in progress.
SDM College FOB: Drawing revised due to SDM management request and  marking on the ground is in progress.
Court Circle :Drawing is under revision at CEPT.

PW 4

Construction of  Pedestrian footpath and NMT Infrastructures in Navanagar and  Dharwad

The UG LT cable laying, fixing of feeder pillar boxes, individual connections to residents. Fixing of bollards is under completion stage and targeted to complete by 15/07/2017.

PW 5

Construction of BRTS Bus shelters from Naveen Hotel Hubli to Rayapur Dharwad

Among 13 bus stations 12 bus stations have been completed. Flooring works at six bus station is under progress and all finishing works which may be completed by July 2017 to August 2017 in phased manner.
Bus station at Unkal village is held up due to shifting of electrical pole & Land acquisition.

  PW6

Construction of BRT Bus stations between Rayapur lake and Bagalokot Petrol Bunk in Dharwad (11 Nos.)

Among 13 bus stations 08 bus stations have been completed. Flooring works for five bus station are under progress which may be completed by July  2017 to September 2017 in phased manner.
Dharwad city limit bus stations ( 5 Nos)  are delayed due to Land acquisition., However planning for diversion of roads and  completing  all the bus station by September 2017

 PW8

Construction of BRT depots at Hubli & Dharwad and Divisional Workshop at Hubli

Dharwad Depot :PQC 1830 Cum out of 1900 Cum completed. Further DLC & PQC works under progress. All finishing works are in progress.
Electrical equipments are under transit.
Targeted completion date: 31.05.2017

Hubli Depot :PQC 2175 Cum out of 4350 Cum completed. Further DLC & PQC works under progress
All finishing works are in progress.
Electrical equipments are under transit.
Targeted completion date: 31.06.2017

Divisional Workshop: DLC 610 Cum out of 1800 Cum  works under progress.
Brick work, water tank works are in progress.
Electrical equipments are under transit.
Targeted completion date: 30.07.2017

PW9

Construction of terminal at Old City Bus Station Dharwad

Block A: First slab concrete completed. Second Slab shuttering and reinforcement is under progress. Ground floor anti terminate is making ready. 2nd slab (RC) Completed.
Block B: Roof slab is completed.
Block D: Water tank and circular ramp work is under progress
Block C:  Ramp wall concrete is under progress. Fabrication work for truss is under progress.
Anticipated date of completion by Sep -2017

PW10

Construction of Regional terminal at existing depot on Hosur  road and Construction of Depot

All building works completed, finishing works are in progress.
Mushroom truss and PQC works are in progress. Retaining wall (RCC) is in progress
Anticipated date of completion by Sep -2017

(ii)Status of Plant/ Equipments and ITS works:

Package

Scope of work

Present Status

PW7

7A- Purchase of Plant and Equipment to BRTS depots and Workshop

Tender process is completed and Letter of Award has been issued to the Suppliers for the supply of 32 equipment.

7B- Purchase of Equipment to Tyre Retreading Plant

Tender has been floated for the purchase of these equipments and 3 bids were received. All the bids were non responsive. Hence retender was floated on 17th January 2017 and the technical bids were opened on 6th March 2017. 2 bids have been received and the evaluation is under progress.

PW 11

11A. Procurement of Intelligent Transport System (ITS) for Hubli-Dharwad BRTS Corridor.

Agreement is entered with M/s NEC India Pvt. Ltd. its consortium on 29/11/2016 for the Design, Supply, Install, Commission and Maintain ITS System for BRTS corridor, duly following the World Bank procurement guidelines. 15 months period has been given for the implementation of ITS system.

11B. Procurement of Platform Screen Doors (PSD) for BRTS bus stations

Agreement is entered with M/s Technocrats Security Systems Pvt. Ltd. on 18/01/2017 duly following the World Bank procurement guidelines. 6 months period is given for the supply and installation of Station Doors.

Turnkey implementation of Adaptive Traffic Control System in Hubli–Dharwad BRTS corridor

Memorandum of Agreement (MoA) is entered with M/s. C-DAC (T), Tiruvanantpuram on 30th Aug 2016 for Traffic Management with ITS, which includes preparation of DPR, installation and operation of ATCS at 43 junctions and 10 midblock locations and setting up of Traffic Management Centre to monitor and manage the signalling system at Hubli-Dharwad BRTS corridor
M/s CDAC has submitted sample junction layout drawings for all the junctions. The sample signal designs for 2 junctions have been submitted and the same is under review.
Note: As decided in the last board meeting held on 04.03.2017, the coordination meeting has been conducted with under the Chairmanship of Deputy Commissioner of Dharwad  on 14.03.2017

Procurement of Rolling stock

1

Procurement of 100 nos of 12 meter, premium, AC, BRTS buses.

The purchase order is placed on M/s Volvo India Pvt. Ltd. for the supply of these buses. The prototype bus is ready and the deliveries are scheduled from  June 2017 to December 2017.

2

Procurement of 30 nos 18 meter, AC Articulated BRTS buses.

The purchase order is placed on M/s TATA Motors Ltd. for the supply of these buses. The prototype bus is approved and the same is under homologation by authorised Certifying bodies.

(iii) Related Works undertaken with GOK funds             

Sl No

Name of the work

Present Status of the work

1

Construction of Compound wall  to the government premises along the BRTS Corridor             ( 1st Tranche)

Completed

2

Demolition/dismantling of the structure from Hosur to Tollnaka.

Work is under progress.

3

Demolition/dismantling  of the structure from Tollnaka to Jublie Circle, Dharwad City

Work is under progress .

4

Construction of Compound Wall to the Government Offices/ School/Garden /Organization along BRTS Corridor in between Hubli and Dharwad (2nd Tranche)

Work is under progress.

5

Construction of Roads opposite to Old Bus stand and HDMC in Hubballi

Road opposite to HDMC is completed. Balance work is in progress.

6

Construction of Compound wall and associated civil works at HDMC & BSNL Sanchar Sadan on Lamington Road, Hubballi

Compound wall work at HDMC is under progress.

7

Transit Oriented Development at Navangar in Hubballi

Financial bid is opened on 05-06-2017. Financial Evaluation is in progress. 

(iv) Works Implemented by KRDCL

A ) Construction of Mixed Traffic Lane Road Work

Sl. No.

Activity

Total Length (in KM) Completed.

Total

LHS

RHS

1

Excavation up to Subgrade TOP

5.240

2.560

17.16

2

Subgrade top

2.680

3.445

3

GSB Top

7.550

6.114

15.65

4

WMM Top

7.526

5.390

15.44

5

DBM Top

6.850

5.376

15.12

v)  Construction of Balance BRTS Corridor: Excavation up to Subgrade work is in progress.
vi)  Construction of 3 Nos Grade Separators:

Sl No

Grade Separator location

Present work

At

Km/Chinage

Total Length

From

To

1

Navanagar

(Ch 6.656)

(Ch 7.51)

854 m

Work completed.

2

Unakal Lake

(Ch: 3.120)

(Ch: 3.575)

475 m

Total 8 Piers , 2Abutments. P3-P4, P4-P5, P5-P6 & P6-P7 Deck Slab work Completed.  Between P2-P3 & P7-P8 girder casting under progress. RE wall casting completed.

3

Unakal Cross

(Ch: 2.325)

(Ch: 2.950)

625 m

Total 16 Piers and 2 Abutments. at A1, P1, P2, P3 & P5 Footing Completed. P8 & P9 Pier wall concreting completed. at P10, P11, P12,P13,P14,P15,P16 and A2 Pier Cap completed. RE panel casting completed..

vii)  Construction of Rail over Bridge (ROB)

Sl No

Components

Progress

1

Test Pile

Testing of Pile Completed.

2

ROB portion Pier Works

All 32 piles concreting completed.  All 4 Pile caps completed

3

Viaduct Portion Abutment Works

All 16 Piles concreting Completed. All 4 Pile caps completed.

4

Vehicle Under Pass

Slab concreting completed on RHS and LHS, except center portion.

5

Cattle Pass

Superstructure Slab completed on RHS and LHS, except center portion.

6

Extension of CD
(pipe culvert)

Slab completed LHS & RHS

7

Construction of CD

RHS wall under progress. On LHS raft work is in progress

8

Tadasinakoppa Village Road

C&G works completed and Earth work is under progress.

9

Drain Work

Preliminary works are under progress.

10

RE Panel cast and erection

4900 No’s of RE panels is casted Out of 10400 No’s. 1400 Sqm RE panel erection completed.

11

Fabrication of Composite Girder

Composite Girder fabrication under progress out of 340 MT, 175 MT fabrication Completed.

12

PSC-I Girders

All 12 PSC girders Completed.

viii) Status of Consultancy services

1

Consultancy for Monitoring & Evaluation for BRTS (Social safeguards)

As per the revised contract, the consultant has submitted interim report. This office has given comments to the consultant. The revised draft final report submitted to this office on 17.02.2017.  We have given the comments to consultant but consultant not submitted final report.

2

Consultancy for Communication and Outreach

Contract period is ended in February 2016. The consultant has carried out all the agreed activities and concept plan has been submitted for pre launch and post launch activities of the operations.

3

Project Management Consultants for BRTS

Consultancy Services was awarded to LASA, Delhi Consultancy services as per TOR are undertaken by LASA.The contract of  PMC is extended up to June 2017. The amended agreement was concluded.    

4

Project Management Consultancy for ITS

The contract is extended from July 2016 to October 2018.  

5

Consultancy Services for Preparation of City Plan for Hubli - Dharwad

The Company has entered into an Agreement with M/s IBI Group On 8th December 2015 for the preparation of city plan of Hubli-Dharwad. The Consultant has submitted the inception report and Summary of Data Gathering & Compilation of   Existing Conditions.

6

Consultancy Services for Environmental Audit

Third Annual Audit for this year is tentatively scheduled in July-2017.

7

Consultancy services for development of landscape plan for Hubli-Dharwad BRTS Project

 3rd Stage of deliverables i.e planting plans, planting list and planting specification is submitted for review and approval.

PROGRESS OF GREEN BRTS PROGRAM:

  • As Per the Green BRTS action plan-
  •  The Company has planted 8000 sapling during the year (2013-14) in the schools, colleges, office premises and public spaces. The Survival rate of saplings till 2016 is 2252 sapling.
  • During 2014-2015, 4000 saplings planted by KFD at Sewage Treatment Plant-Hubli, Nrupatunga Betta & Tapovana. The Survival rate of saplings till 2016 (2nd year) is 3040 sapling and 3rd year survival rate will be known in 2017.
  • During 2015-2016, 1800 saplings planted by KFD at Sewage Treatment Plant-Hubli & Nrupatunga Betta. The Survival rate of saplings till 2016 (1st year) is 1435 sapling and 2nd year survival rate will be known in 2017.
  • In 2016-2017, out of 11600 targeted saplings 10500 sapling are planted by KFD at Navalur Betta and remaining plantation of 1600 with causality is under progress at Navalur Betta.
  • Total sapling planted till date is 24300 and survival rate is 17227.
  • On June 5th, 2017, the World Environmental day a Trail plantation of about 100 tree sapling were planted along the corridor between NGEF to Sanjeevini park for stretch of 0.25km.